Tag: 3621

  • 30/11/25 – Saving A Cylinder

    30/11/25 – Saving A Cylinder

    Hello and welcome to a damp and chilly weekend of progress at Quorn. We dismantle a very corroded vacuum brake cylinder to provide parts to save other cylinders; and make a start with the signwriting on tank 3621.

    During the week I spent a day at Rothley helping the C&W team with some finishing touches to TSO E4982 which was needed for Santa Special duties over the weekend.

    The weather was not kind to us on Saturday, so Harry, Charlie and myself worked in the dry overhauling vacuum brake release valves to put into stock.

    Ross made a start removing the studs from the very corroded vacuum cylinder; some of which were very stubborn and needed a bit of heat to release.

    Once the studs were removed the trunion sections were cut around the edges and will be cleaned up and stored as spares.

    The next step was to cut off the cylinder dome, cutting from the inside using the lower edge of the dome as a guide.

    Centurion ‘Loades’ demonstrating what could be an alternative use for vacuum cylinder parts !

    As the day brightened up Ross cleaned up the edges of dome before this was also put into store.

    The steps that we use to access the Mess Coach have suffered somewhat with rot and need some urgent repairs; in the meantime we moved the steps normally used for visitor access to Test Car 2 into place next to the mess coach.

    Sunday saw more of the team on-site and despite the cold start good progress was made with the tanks.

    Mark, Tom and Oliver cleaning and drying out the chassis end pockets on 3854 ready for paint; and Dan finishing off the Overhead Warning sign on 3606.

    Ross took a look at the re-wiring of the big welder, however on powering-up it became clear that we need a bigger generator to provide it with enough power to work.
    The piston was removed from the Lowfits’ 18″ vacuum cylinder that was started last week and found to be in good order; the marking on the piston confirming that it was last attended to by the Mid Hants Railway in 2008.

    With a little help from Nick aligning the template, I marked out and painted the speed rating stars on both sides of tank 3621.

    Using a bit of spare 3/16″ plate, Ernie flame cut a circle big enough to use as a patch repair for the dome of the 18″ vacuum brake cylinder. Once cut, the plate was placed on an old steel car wheel, heated and given a few blows with a hammer to create a dish shape.

    Nick cleaned up the top of the cylinder and the patch laid in place; Ernie and Ross then made a start welding using the smaller welder.

    Dan picked out the Empty-Load changeover valve lettering on both 3606 and 3621; whilst I added the Commuted Charge Star and logo square to both sides of 3621.

    Oliver, Tom and Mark did some gutter clearing on the Mess Coach and also Test Car 2. They also applied some red-oxide to the cleaned out chassis pockets on 3854.

    Thanks for reading, join us again next week, all the best, Dave

  • 19/10/25 – More Tank Progress

    19/10/25 – More Tank Progress

    Hello and welcome to the news from Quorn; this week tank 3606 gets its identity back and we make more progress with tank 3854.

    We also have news that three vehicles which have been long term residents at the GCR have now passed into Quorn Wagon & Wagon custodianship. These being 20T tank wagon A6071, 22T Lowmac EO DE269001 and 20T Herring Ballast Hopper DB992447. More details of each wagon can be seen by clicking each text link above.

    Dan and myself made a start preparing the pre-printed templates, measuring and marking out for the lettering on 3606. It quickly became clear that we had bit of a problem with an somewhat errantly placed OHL warning plate on one side of 3606. Measuring up all the other wagons of this type confirmed that the plate is some 12″ further to the left therefore clashing with the Esso Petroleum barrel side lettering. This may indicate that this particular tank did not originally have the full Esso Petroleum lettering (not all did).
    After much discussion (and cursing that we had not picked this up before we applied the paint), we decided that it would be easier to remove the plate, grind the welds flush and patch-in the paintwork. A replacement OHL warning plate will be created by signwriting further along the barrel to match the other wagons.

    Dan then started the west side solebar lettering whilst I concentrated on the running numbers.

    Ross, Harry, Charlie and Daniel got to work overhauling the next vacuum cylinder which will be fitted to tank 3854 in due course.

    Work continued on repairs to 3854s spark guard plates.

    Mark, Oliver and Tom made good progress with paint stripping on tank 3854, whilst James had a lesson in axlebox painting.

    The tank end running numbers were also applied before the weather turned on us again.

    The broken label clips on both sides of 3606 were replaced with serviceable spares; both being somewhat stubborn to remove due to corroded bolts.

    Thanks for reading, join us again next week; all the very best, Dave

  • 12/10/25 – Bit of a pea souper!

    12/10/25 – Bit of a pea souper!

    Hello everyone and welcome to this weekends update. Today’s been a bit of a foggy one for us which didn’t really let up until after lunch.

    After turning 3854 in the week to allow for access, Mark, Tom, Oliver and Dan made a start on the other side of 3854, using the needle guns to bare metal the ‘belly’ of the tank barrel. The rest of the barrel will be done with the abrasive paint removal discs on the grinders, as per the other side.

    James, Charlie, Dan and I started cleaning up the brake shoe hangers after which Dan followed behind and applied some black gloss.

    Dan also applied white undercoat the the axle bearing end caps, handbrake levers and lamp brackets.

    With assistance from James and Oliver, Nick stripped the floor from the Conflat, ready for it to be taken to the bonfire construction area.

    Charlie and I repaired the motor cabling on George and got the field reversing switch wired back up to put him back into use. He was quickly placed into work moving the floor removed from the Conflat to the bonfire pile.

    I showed Charlie and Dan how to adjust the brakes on the BEVs, and left Charlie to adjust the ones on George and Zsa-Zsa.

    After cleaning down, Tom, Mark and Oliver followed behind where they had bare metalled with grey primer/undercoat.

    On Sunday, Ernie and I looked at some more welding on the spark/splash guards from 3854

    That’s everything for this week, join us next week to see us hopefully start signwriting the two tanks, and getting further with the work on 3854. Thanks for reading!

  • 05/10/25 – 2nd Coat Applied

    05/10/25 – 2nd Coat Applied

    Hello and welcome to our news from the Autumn Steam Gala weekend. The weather has been kind enough to allow us to get the second coat of gloss black on both tank wagons 3606 and 3621. We’ve also progressed preparation work on tank 3854.

    The Steam Gala weekend was a great opportunity to see some of our goods wagons in operation, with the mixed and the vans operating throughout the weekend.

    On Saturday Nick, Ernie, Mark, Harry, Tom, Oliver and Dan made good progress with the needle guns cleaning up the underframe and the west side of the tank barrel on 3854.

    Red oxide primer was applied to the cleaned up areas of the underframe.

    On Sunday whilst myself and Ross prepared the paint and spraying equipment Charlie and Ernie continued with their work repairing the spark guards for tank 3854.

    Nick spent the day continuing with the needle gun cleaning up the East side underframe of tank 3854.

    The tank barrel of 3606 was sprayed first.

    Then the barrel of 3621, followed by the soldbars of both wagons.

    The next stage for both 3606 and 3621 is touching up and painting the details such as axlebox covers and brake swan necks, followed by the signwriting of the Esso lettering on the barrels and solebar information.

    Join us next week to see how we get on; all the best, Dave

  • 28/09/25 – Getting ready for the second coat

    28/09/25 – Getting ready for the second coat

    Hello everyone and welcome to another update from Quorn. This week we’ve prepped both 3606 and 3621 for their second coat of paint, and 3854 has received a bit more work on the underframe to clear the corrosion.

    James, Charlie and I spent most of the day scuffing the fresh black paint. We managed to get both east side barrels done and three of the four ends. While we did this, Ernie sorted some donated large spanners and impact sockets away

    Nick, Harry, Tom, Mark and Dan continued the push on 3854, using the needle guns and hammer and chisels on the end pockets and the solebars.

    Oliver and Charlie finished repairing the hand rail to the tool van

    The team also finished scuffing all the areas on the two tanks missed

    That wraps up this week, and sorry its a bit of a late one! I’m travelling for work again so this is the only chance I’ve had! Join us next week where hopefully the tanks will have received their extra coat. Thanks for reading.

  • 21/09/25 – Twin black tanks

    21/09/25 – Twin black tanks

    Hello everyone, and welcome to another update from Quorn. This week, we’ve finally been able to get some paint on both 3606 and 3621 which marks a big step forward in their restoration, especially given the recent abrupt end to the summer.

    While Dave and I got the equipment assembled and ready, Ernie, Daniel, James and Nick completed some final preparation work on the tanks.

    Our new paint pot is an upgrade, we now have capacity for 10litres of paint up from 2, which means a lot less time spent mixing and filling up the tank! Dave and I used 12 litres of grey primer/undercoat over both 3606 and 3621. We had to spent a little bit of time avoiding/ drying up after small showers during the day, but we were able to get both tanks into undercoat, save for the portion of the under fame below the dock.

    While Dave, Nick and I got the tanks painted, Charlie and Ernie made a start welding up the splash guards for 3854. Nick assisted with bending up a new end for one of the pieces.

    For Dave and I, Sunday was pretty much a rinse and repeat of Satruday, only this time with black gloss paint, rather than grey! Nick and Oliver assisted with some spot drying of the tank barrel and underframe. We’ve opted to try some skip and container paint on these as an experiment. Tom got some undercoat on the underframe on the parts of the tanks below the dock, and he was willing to have a go with the spray gun.

    Nick and Oliver ended up going to Swithland to look at 80307, which was noticed to have had a window blank fallen inside the vehicle. This has been fitted since it arrived, and had fallen out in the wind. The piece was refitted, and sealed back to the door for the time being.

    Charlie and Ernie carried on with the weldeing until the generator ran out of petrol, after which Charlie and Oliver started to repair the steps up to the tool van.

    Tom finished up the tank; by taking the spray gun below the dock again and spraying up the underframe. A second coat is required for both tanks, but we’re glad we’ve got them both started!

    That wraps up this weekend’s work, We’ll have to sort out a second coat for the tanks at some point soon, and then its on with the signwritng. Plus we’ll have to sort out the Esso plates! I’m not sure what the plan is for next week, we are very dependent on the weather at the moment, so join us next week and see what we end up doing! Thanks for reading, Ross

  • 14/09/25 – Palshoc Re-Wheeled

    14/09/25 – Palshoc Re-Wheeled

    Hello and welcome to two-weeks’ of news from the team at Quorn. The Palshoc Body has been united with its chassis; Edward is now up and running; we’ve visited the Foxfield Railway, and we continue to progress the tanks; although it’s still been a bit damp for paint. We’ve also been attending to the BEVs.

    The repairs to Edward continued with a new water pump, new thermostat, new fuel lift pump; the injection pump was re-sealed and the back half of the exhaust was re-made with a flexi-pipe and a new silencer/tailpipe. The exhaust manifold gasket was also replaced. After he was re-assembled, fluids were filled up and his casing bolted back on. Edward now running much sweeter ready to reliably supply the air we need for paint spraying.

    On Sunday 7 September, Nick and Charlie took a trip across to the Foxfield Railway to recover some kindly donated parts from a redundant Esso tank chassis. A brake change-over lever & associated pipework/rods, a tank drain valve, end pipes and brackets are all parts that are needed for the tanks that we are restoring.

    At Rothley on Monday 8 September we assisted the C&W team with the recovered Palshoc & chassis work. After some careful sanding of the van body we have revealed its identity, B855568.

    The chassis was lifted and its wheelsets replaced with a set acquired from Ruddington. The bearings and journals were examined, axleboxes cleaned, pads fitted and oiled-up.

    The Palshoc body was lifted into place on the chassis, positioned and levelled, then welded at each corner to allow the wagon to be shunted safely.

    Tank 3854 – the headstock frame box areas were cleaned out and sanding of the tank barrel has been progressed.

    Tank 3606 – A final sand of the tank barrel was completed; the recovered brake change over levers and rods were cleaned up and fitted.

    Tank 3621 – The change-over levers were freed off, oiled up and the lever bracket castings cleaned up.
    A final bit of sanding was carried out of the tank barrel.

    Due to the inclement weather the painting of the tanks has been postponed again, however we have acquired some new spraying equipment and this was prepared ready for when the weather provides as suitable opportunity.

    Two of the BEVs have recently been giving a few problems, George suddenly stopped powering and Kiki‘s resistor bank overheats very quickly. We made a start investigating the problems, firstly to get acquainted with how they are electrically connected we drew -up a schematic for both BEVs. Quite quickly we saw that they were not the same, after checking ZsaZsa we concluded that Kiki was not wired correctly, also the top panel of her resistor bank was somewhat corroded which may have contributed to the overheating.

    Checking of the cable continuity on George revealed that the power was not getting from the controller to the motor; further investigation removing the cable protection found a fractured power cable. This will be repaired and a new protective sheath fitted to the motor cable loom.

    The resistor bank from Kiki was removed and replaced with a spare we had. This will be wired up correctly in due course.

    With the mixed goods rake stabled in the yard, Dan took the opportunity to finally apply the dates and depot codes to the data panel on the Coal Hopper B425356. He first created a template which provided the outline once chalked to the wagon as the guide for signwriting.

    That concludes what has been a couple of weeks of very varied work; join us again soon when we hope to hope to get the opportunity to apply some paint to the tanks.

  • 25/8/25 – Bare barrels, a poorly Edward and a finished TTB

    25/8/25 – Bare barrels, a poorly Edward and a finished TTB

    Hello all, and thanks for reading this week’s update from Quorn. This weekend, its been a case of getting 1919 ready for release to traffic and pushing on with the Esso (3606, 3621 and 3854) tanks to get them ready for paint.

    3621 and 3606 got a last bit of sanding and preparation to remove what has been revealed through the coat of primer. A bit of make do and mend came into play with the sanding disc not sticking to the backing pads. We’ll have to get some more on order!

    We took the opportunity with many hands to remove 1919 from the dock and collected together the three Esso tanks on the dock road, after which I removed the OLE warning flashes from all three.

    A quick before and after with 1802 and 1919

    1919 sat on the middle road where Dave touched in some of the black paint and prepared the logos for a coat of varnish. Ernie and Harry replaced the hand rail into the coach after several of the team had received splinters from the last one.

    Dave sign wrote the OLE flashes onto 1919, and then applied a coat of varnish over the Shell and BP logos to ensure their longevity. The sanding continued, though the compressor seemed to be struggling and nearly stalling. The fuel pump has developed a serious leak, so it is time for some long overdue TLC for Edward.

    I concentrated on welding the blanks to 3606 to cover over where pipes had been installed for its static use. Nick and Ernie looked at removing a tray that had been installed to 3854 and Ernie tidied up the weld remnants.

    Dave and I undertook the final inspection of 1919, checking it before output and completing our form ready to hand over to Jamie. I checked the flange gauge against the calibration specification, and found it to be spot on. With help from Tom and Dan, we undertook a test of both the air braking system and the vacuum through pipe. The through pipe was satisfactory, however the air brake system appear to not be working which requires further investigation.

    The team undertook another shunt to release both 3606 and 3854 to turn them on the turntable. This allows us easy access to both vacuum cylinders, the former to refit and the later to remove and overhaul.

    Edward was stripped and drained down, with some other issues found including a failed water pump bearing and the silencer no longer being connected to the exhaust. Charlie and Dan gave everything a few coats of heavy duty degreaser and washed it off, making it a lot easier to trace any further leaks.

    With 3606 been turned, Nick decided to refit the overhauled vacuum cylinder with assistance from Oliver and James.

    Mark, Tom and James concentrated on the last bits of old paint and tar on 3606, which is now ready for primer.

    Edward has become top priority now as we need him for compressed air, but we’ll keep moving with the tanks and get them painted. Come sand see how we get on next week. Thanks again for reading!

  • 17/08/25 – Railways at Work 2025

    17/08/25 – Railways at Work 2025

    Hi all, welcome to a Railways at Work weekend update. Whilst some of the team supported the event, the rest continued with work on two of the tank wagons; and at Rothley the C&W department team have progressed repairs to the Lowfit and also the Steel High.

    At Rothley the repair work on the wagon end sections of Steel High B724570 was well advanced. Thanks again to Jamie, Pat, Kyle, Rob, Noah and Steve.

    Also the C&W team had welded new metal into the dragbox of the Lowfit B452718, (thanks to Pat for the photos)

    On Friday preparations for the Railways at Work weekend involved getting the barrels and Brute Trolleys out of the van train at Quorn.

    Over the weekend Mark, Tom, Ernie and Oliver continued to progress cleaning down and applying red-oxide primer to tank 3621.

    Oliver had a birthday celebration; and of course there was cake involved….

    Tank 3606 also received attention with some primer and undercoat applied to underframe areas.

    The Railways at work is always an enjoyable weekend; here’s a selection of our pics.

    and the Railways at Work team.

    Thanks for reading, join us again next week, all the best, Dave

  • 10/08/25 – Large Logos, Lugs and a little bit of welding

    10/08/25 – Large Logos, Lugs and a little bit of welding

    Hello everyone, and welcome to another update from Quorn. Now that I’ve come back from the frivolities of my wedding and from staffing HydroFLEX at the Greatest Gathering, I’ll give you a run down of what has happened for us this week.

    At Rothley, good progress had been made by the C&W team on both the Lowfit with its previously poorly dragbox and the shock absorbing High Goods with its rotten corrugated end being replaced for some spare good material. Additionally, the Lowfit chassis has received more black paint and the chassis for the Palshocvan body had been needle gunned and primed, getting it ready for the body to go on. Thanks to Jamie, Pat, Kyle, Rob, Noah and Steve, we’re looking forward to having these back and getting them in traffic.

    The week prior, the tank train had applicable vehicles receive a bearing exam and all vehicles had their brake rigging oiled.

    On to this weekend then, and after my time away its nice to see the amount of progress that has been made. Before the trains started running, Charlie (with Nick as lookout) mowed the grass between Road 1 in the South Yard and the running line.

    Dave got started on the east side Shell logo, getting it chalked up and completed in the morning.

    Ernie and I got the Esso plate jig out and welded the plate brackets back on to 3621. We started on the west side, and the jig made the work really easy, though the height from the ground did add a complication. I modified the jig to allow a bit of access to the bottom ring from the top which made the east side lugs even easier. the west have been fulled welded, and then received a dose of wire brushing by Nick and painted with a coat of primer by James. I ran out of 3.2mm electrodes before finishing the west side, but we can catch that at a later date.

    Dave got the west side Shell logo on 1919 and touch up the green on the BP logo. This is among the last jobs on this tank, though we will be varnishing each of the logos on this tank. That leaves us to complete our paperwork before handing it over to Jamie for its acceptance FTR. I measured the flange height and thicknesses, which were showing a nearly brand new P5 profile. Dave applied a wheel 1 arrow to the tank to assist us in future inspections.

    3621 had its lid securing turnbuckles freed off and oiled courtesy of Charlie and Ernie, plus an extra pipe stub in the filler neck was removed and blanked and Nick got the scaffolding down to 3606 to scrape the the tar residue from around the filler neck and around the top of the barrel. This needs a bit more scraping and a bit of degreaser before we can paint it. I went round 3606 with the big ratchet to make sure that all the side support bolts were tight. I’ll be adding a blob of weld to each exterior bolt to ensure that they don’t come undone.

    Ernie used an angle grinder to clean up the support remnants on 3606. Nick, Charlie and James took the washer tin over to 3854 to put new washers in the brake system where they were missing.

    Lastly, Charlie and James gave the BEVs a clean and a charge before Railway at Work next weekend. Do come down to the railway next weekend to experience the sights, sounds and atmosphere of a by-gone era, showing how goods and passengers were moved around the network. We’ll be there helping to tell the story. Join us then!