09/02/24 – Happy birthday, Tom!

Hello everyone and welcome to another update from Quorn. We’ve finished the through pipe on 1802 which is now fully fitted but not yet tested. This just leaves the same pipe to make on 1919, which we’ve made a good start on.

Firstly, we wish Tom a happy 18th birthday!. Tom’s family very kindly sent along some lovely cakes last week (which I should have mentioned, sorry!).

First action on the tanks was to remove the pipework as fitted to 1802 to use as a template for the pipe on the 1919. While the pipe was in I measured up to make the last pipe bracket. We also got the heat gun out and adjusted the two dummy brackets fitted to 1802.

With the heat gun out, we shunted the Lowfit on to the end of the tanks to sort the last remaining bent corner on the west door.

Ernie and Nick started looking at the bits of pipe we have in stock to match them up to the pipe from 1802, then the pipe cutting and threading continued, with new recruit Harry having a go on the pipe threader.

I welded up the pipe bracket, getting it ready for fitting. The team got the pipes fitted back into position, while the 6 pipe brackets were fitted with locking nuts. Some hardwood packers have been fitted in some positions to minimise the stress to the pipework.

Some of the pipe remnants seems quite hard, so required annealing with the heat gun before being manipulated for 1919.

The Baldwin lads (with some interjection by Charlie) started a secret project on the dock with some scrap wood. Dan was caught having a sit down… Tom and Mark did some touching up on the undercoat north end of the GUV. Dave and Ernie had a brief break by fixing one of Nick’s lamps.

Last thing to do was christen 1802 and fit some vacuum bags. Next week this will be leak tested alongside the air brakes, and the pipe work on 1919 should be very close to being finished. we’ll then get organised for the TEA, maybe with a brief interlude to play with a recently delivered new toy! Join us then and see how we get on!