Hello everyone, and welcome to another update from Quorn. Now that I’ve come back from the frivolities of my wedding and from staffing HydroFLEX at the Greatest Gathering, I’ll give you a run down of what has happened for us this week.
At Rothley, good progress had been made by the C&W team on both the Lowfit with its previously poorly dragbox and the shock absorbing High Goods with its rotten corrugated end being replaced for some spare good material. Additionally, the Lowfit chassis has received more black paint and the chassis for the Palshocvan body had been needle gunned and primed, getting it ready for the body to go on. Thanks to Jamie, Pat, Kyle, Rob, Noah and Steve, we’re looking forward to having these back and getting them in traffic.
















The week prior, the tank train had applicable vehicles receive a bearing exam and all vehicles had their brake rigging oiled.
On to this weekend then, and after my time away its nice to see the amount of progress that has been made. Before the trains started running, Charlie (with Nick as lookout) mowed the grass between Road 1 in the South Yard and the running line.

Dave got started on the east side Shell logo, getting it chalked up and completed in the morning.






Ernie and I got the Esso plate jig out and welded the plate brackets back on to 3621. We started on the west side, and the jig made the work really easy, though the height from the ground did add a complication. I modified the jig to allow a bit of access to the bottom ring from the top which made the east side lugs even easier. the west have been fulled welded, and then received a dose of wire brushing by Nick and painted with a coat of primer by James. I ran out of 3.2mm electrodes before finishing the west side, but we can catch that at a later date.




Dave got the west side Shell logo on 1919 and touch up the green on the BP logo. This is among the last jobs on this tank, though we will be varnishing each of the logos on this tank. That leaves us to complete our paperwork before handing it over to Jamie for its acceptance FTR. I measured the flange height and thicknesses, which were showing a nearly brand new P5 profile. Dave applied a wheel 1 arrow to the tank to assist us in future inspections.








3621 had its lid securing turnbuckles freed off and oiled courtesy of Charlie and Ernie, plus an extra pipe stub in the filler neck was removed and blanked and Nick got the scaffolding down to 3606 to scrape the the tar residue from around the filler neck and around the top of the barrel. This needs a bit more scraping and a bit of degreaser before we can paint it. I went round 3606 with the big ratchet to make sure that all the side support bolts were tight. I’ll be adding a blob of weld to each exterior bolt to ensure that they don’t come undone.


Ernie used an angle grinder to clean up the support remnants on 3606. Nick, Charlie and James took the washer tin over to 3854 to put new washers in the brake system where they were missing.



Lastly, Charlie and James gave the BEVs a clean and a charge before Railway at Work next weekend. Do come down to the railway next weekend to experience the sights, sounds and atmosphere of a by-gone era, showing how goods and passengers were moved around the network. We’ll be there helping to tell the story. Join us then!