17/10/21 – Back on the brakes

In this week’s update, we’ve continued working on the Bogie Bolster’s brakes and have started a mass tidying and sorting activity.

Welcome to another update from Quorn, which leaves me following up on Dave’s fantastic first update. As a team, we’ve continued looking at the brakes on the Bogie Bolster and starting to sort out for the long-anticipated return of the Living Van, which sadly hasn’t happened this weekend as was previously rumoured. We are still passing best wishes to Matt who is still feeling under the weather.

Dave, Jake and I looked at the brakes on the Bogie Bolster, targeting problem areas. The Gloucester 3 piece bogies don’t have hangers for the bow girders and instead use an inclined pocket to guide the blocks to the wheels. Due to lack of use, some of the bow girders had seized in the pockets which could mean that the brakes either wouldn’t work or would apply and not be able to adequately release.

By removing the stop bolts, we were able to slide the bow girder out of its pocket adequately to clean them out. After this, we applied oil to the sliding surface and resituated the bow girder in its pocket. We repeated this process on the south end bogie. This has ensured the brakes on the bogie apply and more importantly release under their own mass.

I removed the unserviceable slack adjuster from the north end brake rigging. I’ll ring around some firms in the week to see if we can get such an item overhauled (while we are at it, we might as well have both done!)

Richard was able to rejoin us this weekend, and spent his time scraping the north end bogie frame and made a really good job of it. Jake and Nick went to Rothley to retrieve some of the tools we’d left in the Living Van as we’d been struggling without them, mainly the angle grinders and the axlebox maintenance kit. The last thing we did on Saturday was to liberate some steel cupboards from the van train so that they can be used in the GUV or Living Van to improve our storage situation.

The first half of Sunday saw just Dave and I start the task of tidying and sorting the GUV. At this stage, we are just getting rid of any rubbish before re-shuffling items around when the Living Van returns. Eddie was with us and continued scraping and prepping the underframe of the BoBol. He started on the south end bogie frame and did the same amazing job as Richard. Once finished on the bogie frame, Eddie continued on the trussing and solebar.

At the end of the weekend, Dave and I had made four dumper runs up to the skip and cleared all of the surfaces in the GUV. As a team, we’ve also ticked a few more jobs off the to-do list on the Bogie Bolster. Next weekend should see more of the same, with more work on the bogie bolster and probably some more tidying.

Author: Ross Loades

Wagon Basher and Systems Engineer in the Rail Industry